PRIMARY CONTRACTOR FRAMEWORK 2021 - PORTSMOUTH & SUB REGION

Award

Value

£378,555

Classifications

  • Building construction work
  • Miscellaneous building structures
  • Building fittings
  • Site preparation work
  • Roof works and other special trade construction works
  • Building installation work
  • Building completion work
  • Hire of construction and civil engineering machinery and equipment with operator
  • Repair and maintenance services of building installations
  • Architectural and related services
  • Landscape architectural services
  • Construction-related services
  • Technical testing, analysis and consultancy services

Tags

  • award
  • contract

Published

2 years ago

Description

Portsmouth City Council - the "Council" - has established a new Primary Contractor Framework. Contractors are able to undertake a range of multi-disciplinary project work on a Principal Contractor basis.
The Framework will serve as the primary route to procure building maintenance and to a lesser degree construction projects for Building Services within the Council, with works generally being undertaken to the Councils portfolio of nearly 15,000 social housing properties and 900 corporate assets.
The award of the framework agreement is 26th July 2021 and will be available to use for 4 years until 25th July 2025.
The framework agreement was established via evaluation of tenders submitted for Phase 1 works on Dunsmore Close flats 26-44, which comprises of a repair and improvement scheme to Local Authority blocks of flats.
Upon completion of Phase 1, the Council reserve the right to directly award a further two phases of works for additional blocks of flats for Dunsmore Close to the successful tenderer.
The estimated value for the works are -
• Phase 1 - £350K
• Phase 2 - £800K
• Phase 3 - £450K
The preferred bidder, D.M.Habens Ltd, and the next 12 highest-ranking contractors have been  appointed onto the framework agreement, split into a primary tier of 6 contractors and a secondary tier of 7 contractors.
Typically works include but are not limited to;
• External and communal decoration
• Window replacement
• Roofing replacement
• Fire Door replacement
• Electrical works
• Fencing
• External repair to brickwork and concrete structures
Other projects may involve but are not limited to;
• Conversion of properties
• Refurbishment of properties
• Extensions
• Disabled adaptations
• Construction projects
It is forecast that the majority of projects, around 80% based upon historical demand, will be to the Councils social housing portfolio where residents usually remain in occupation for the
duration of works. 
Although only a forecast subject to variation, the remaining 20% of projects are likely to be in relation to maintenance / construction of properties within the Councils varied corporate property portfolio, this includes properties such as;
• Schools
• Libraries
• Leisure centres
• Social Care Facilities
• Depots
• Commercial Buildings
• Community Centres
• Cultural assets
• Shops
It is anticipated that over the 4 year period up to £60m of PCC projects may be procured through the Framework based upon the agreed maintenance budget for 2021/22 and predicted budgets for future years.
Factoring in potential additional use by the PCC and use from other contracting authorities that will be able to access the framework agreement, either directly or via PCC, it is
anticipated that the maximum spend on the Framework could be as much £100m, although no commitment can be made in this respect.
Typically the majority of projects will range from £100k - £250k however there will be frequent occurrences where project values are below £100k ranging up to above £1.5m. There is no minimum or maximum project values as whilst the contract value ranges may differ the core work is of a similar nature.
The framework has a primary and secondary tier, whilst allowing for award of call off contracts via mini-competition and direct award against a range of options. Further details
on who can access the framework, the contract award provisions and operation see section II.2.4.
The procurement was undertaken in accordance with the Open Procedure as defined within the Public Contracts Regulations (2015).
Application was via submission of completed tender via the Council's e-sourcing system accessible via: https://in-tendhost.co.uk/portsmouthcc/aspx/home which was used to administrate the procurement process.

Documents

Premium

Bypass the hassle of outdated portals. Get all the information you need right here, right now.

  • Contract Agreement

    The official contract terms, conditions, and scopes of work.

    Download
  • Award Notice

    Details on the tender award and selected suppliers.

    Download

Similar Contracts

Open

Multi Disciplinary Design Team

St Osyth Priory & Parish Trust is currently in the development phase of a National Lottery Heritage Fund grant which will focus on the redevelopment of the Tithe Barn and Old Dairy and into hireable event and community spaces. St Osyth Priory and Parish Trust wishes to appoint a suitably qualified and highly experienced Multi Disciplinary Design Team to work on the Development and Delivery Phases - RIBA 2 to RIBA 7 of this aspect of the project. This ITT sets out the background to the project, the tender process, timescales, and management arrangements. There is, however, no guarantee that Delivery Phase services will be required, and bidders should take account of this. Below is an approximate timeline of the programme: RIBA Stage 2 - July 2025 - December 2025 1. Pre-planning Application Submitted - September 2025 to November 2025 2. Ongoing SOPPT Meetings RIBA Stage 3 - December 2025 - August 2026 1. Coordinated Designs & costs Approved - May 2026 2. Match Funding for Delivery Phased secured and in place, agreements in place - May 2026 to August 2026 3. Planning/LBC Applications - April 2026 - May 2026 4. Delivery Phase Application Prepared - June 2026 - July 2026 5. Delivery Phase Application Submitted - August 2026 6. Planning/LBC Decision - TBC 7. Ongoing SOPPT Meetings End of Development Phase RIBA Stage 4 - January 2027 to June 2027 1. Decision on Delivery Phase Application - December 2026 (TBC) 2. Estimated Permission to Start Received (Delivery Phase) - January 2027 3. Discharge Pre-Commencement Planning/LBC conditions - February 2027 to May 2027 4. Ongoing SOPPT Meetings RIBA Stage 5 - November 2027 to January 2029 1. Construction - December 2027 to October 2028 2. Fit out and interpretation installation period - November 2028 to January 2029 3. Ongoing SOPPT Meetings RIBA Stage 6 Handover of sites & testing for close out - January 2029 - March 2029 1. Ongoing SOPPT Meetings RIBA Stage 7 In use and open for Autumn - March 2029 - May 2029 1. Ongoing SOPPT Meetings 2. Project Evaluation Submitted - March 2029 to May 2029 3. Activity period and programme ends - May 2029 SOPPT will also be procuring or have procured the following Consultants to comprise the Project Team: • Project Manager • Quantity Surveyor • Multi-Disciplinary Design Team • Activity Plan, Community Consultation and Co-Production Consultant • Business Planner • Evaluation, Economic and Social impact Consultant • Fundraising Consultant • Others as required The current anticipated construction value is £2.908 million excluding VAT, inflation, contingency and fees. All applications, enquiries and requests for site visits need to be sent to [email protected] What to include: - Case Studies - Details of who will be involved, including Bios and CVs - Community and Stakeholder Engagement - Methodology and Timeline - References - Insurance - Social value - Cost breakdown

AI Bid Assistant

Our AI-powered tool to help you create winning bids is coming soon!

View Contract Source Save Contract

Organisation

Procurement Service

[email protected]

+44 2392688235

+44 2079476000

Timeline complete

Publish
Bid
Evaluate
Award
Complete