Description

The Council is looking to appoint a single competent principal contractor to undertake decarbonisation works at the New Art Gallery Walsall. The project comprises of the following items to be partly funded by Salix via the PSDS 3c: 
      
      o Strip out and removal of the existing gas boilers. 
      o Replacement of the inverted roof system with new warm roof deck on the 4th floor to provide a 20-year insurance back warranty.
      o Installation of new handrail system to the roof and bigfoot system for ASHPs.
      o Installation of new ASHP and Water to Water Heat Pumps. 
      o Associated fire-stopping works. 
      
      The Council procured expert consultants to undertake carbon auditing across its estate including leisure facilities. For the New Art Gallery the following measures have been recommended, funding permitting: 
      
      o Installation of an air source heat pump. 
      o Installation of secondary glazing. 
      o Installation of tap flow restrictors. 
      o AtkinsR?alis have made a strategic assessment of the economic and sustainable approach which is the installation of a renewable heating system (air source heat pump). The proposal is to install:
      
      - Install a Mitsubishi NX-N Range air source heat pump with a 400v 3ph 50 Hz Phase Power plus DOL starter. 
      - Install an accompanying Mitsubishi EW-HT range water-to-water heat pump with a 400v 3ph 50Hz Phase Power output. 
      - A structural survey has been undertaken identifying the lower roof of the Gallery as being the only suitable location for the air source heat pump to be installed. The loading of the unit is to be spread using a Big Foot load spreading system.    
      - The annual forecast energy savings following the works is estimated to be 270,684kWh.
      - Reduce the carbon emissions by 86.04tCO2 per year based on the Salix PSDS 3C application.   
      - The investment will provide an immediate impact on the heating and energy demands of the Gallery. 
      
      Programme
      Designs provided within this tender are up to RIBA Stage 4. 
      
      The Council aim to award the contract by 7th March 2025 and works to be completed at the earliest opportunity subject the manufacturing lead times/weather conditions, envisaged July 2025.
      
      The route to market being used is a direct award under the Pagabo Decarbonisation  Solutions framework. The framework is 0.25%, which is charged monthly to the winning contractor. 
      
      Budget
      Circa ?798,000.00 of which ?332,583.99 comprises of grant funding provided by Salix. 
      
      Under the grant funding terms, all grant funding must be drawn down and spent by the 31st of March 2025.  
      
      Insurance Requirements
      o Employers' liability - a minimum of ?5 million.
      o Public liability - a minimum of ?10 million.
      o Professional indemnity - a minimum of ?1 million 
      
      Procurement Timetable
      Set out below is the proposed procurement timetable. This is intended as a guide and, whilst the Council does not intend to depart from the timetable, i...

Documents

Premium

Bypass the hassle of outdated portals. Get all the information you need right here, right now.

  • Contract Agreement

    The official contract terms, conditions, and scopes of work.

    Download
  • Award Notice

    Details on the tender award and selected suppliers.

    Download

Similar Contracts

Open

Fochriw Primary School – Roof Replacement

You are invited to submit a tender for the replacement of the lower block roof at Fochriw Primary School. The scope of the project is fully described in the tender documentation but in summary the scope is: - Provide and erect fixed scaffolding with built in stairs, hoists for materials, and including additional protection over all maintained entrance/exit and fire escape doors, double boarded fans, kick boards, brick guards on handrails, netting and any post protection padding as may be necessary, etc. - Removal of existing brick chimney stack to below roof level - Ceiling repairs in classroom 024 & 027. - Pitched Roof Renewal of lower infant’s block. - All works must be carried out and completed over the summer period between 21st July – 29th August 2025 - Allow for all necessary protection to existing flat and pitched roof areas not included in these works. - Elevations to be fully scaffolded, must include fixed staircase and internal barrier to floor edge. - Heras anti climb fencing to be erected around the complete perimeter of the scaffolding, a minimum 1-2m outside base of scaffolding, to provide complete segregation between works and building/school users. - No Doorways, gates or walkways are to be blocked off during the execution of these works without the prior written consent of the contract administrator. - Removal, safe storage, refit and commission of existing PV/solar panels. - To the areas noted on drawing number A001, provide and fit new Redland Cambrian roof coverings including all new lead gutters, valleys, flashings, structural roof battens, breathable under cloak, and all necessary ventilation, etc. - All to be as the attached BMI Redland specification reference: SM-12- 000806. - Lead to be Code 5 to gutters and valleys with Code 4 to be used everywhere else. - Form new lead collars and soakers where existing pipework penetrates the roof. - To all areas that will receive new roof coverings, provide and fit new rainwater goods. - To all areas that will receive new roof coverings, provide and fit/overclad existing with new soffit/bargeboards.

Katy Reed

Published 1 week ago

AI Bid Assistant

Our AI-powered tool to help you create winning bids is coming soon!

View Contract Source Save Contract

Organisation

Stacey Hackett

[email protected]

123456

Timeline complete

Publish
Bid
Evaluate
Award
Complete