Description

Construction Plan
1.	Scope of Works. The works will include:
• Site preparation and demolition of existing fence.
• Earthworks, grading and sub-base preparation.
• Installation of drainage systems.
• Construction of reinforced concrete skatepark elements (bowls, ramps, platforms, coping).
• Installation of street-style features (rails, ledges, stairs).
• Perimeter works including pathways and landscaping.
• Site clean-up, quality checks, and handover.
2. Methodology
2.1 Mobilisation
• Establish site compound, temporary fencing and signage.
• Set out works in accordance with approved design drawings.
• Conduct pre-start meetings with subcontractors and suppliers.
2.2 Site Preparation
• Clear vegetation, debris and unsuitable materials.
• Carry out excavation to design levels.
• Import and compact subgrade fill where required.
2.3 Drainage & Utilities
• Install sub-surface drainage to prevent water pooling.
• Connect to existing stormwater infrastructure.
• Install conduits for future lighting and services.
2.4 Concrete Works
• Coping and edging hot dipped galvanised. Cut ends to be treated with corrosion resistant paint system
• Formwork, steel reinforcement and shotcrete application for bowls and ramps.
• Machine finishing followed by hand-trowelling for smooth riding surfaces.
• Expansion joints, coping stones and steel edges installed.
2.5 Ancillary Works
• Install prefabricated hot dipped galvanised rails, ledges and modular features.
• Construct pathways, seating areas and viewing zones.
• Landscape the surrounding area.
3. Health, Safety & Environmental Management
• Works to be carried out in accordance with [local construction safety legislation].
• Dust suppression and noise control measures.
• Daily toolbox talks and risk assessments.
• Waste management and recycling plan.
• Public safety maintained through secure site fencing and restricted access.
• Working hours 0800 to 1700.
• All operatives working on site should have relevant CSCS cards.

Documents

Premium

Bypass the hassle of outdated portals. Get all the information you need right here, right now.

  • Contract Agreement

    The official contract terms, conditions, and scopes of work.

    Download
  • Award Notice

    Details on the tender award and selected suppliers.

    Download

Similar Contracts

AI Bid Assistant

Our AI-powered tool to help you create winning bids is coming soon!

View Contract Source Save Contract

Timeline active

Publish
Bid
Evaluate
Award
Complete