GMCA 825 Household Waste Recycling Centre at Reliance Street, Manchester

Complete

Value

£4,500,000

Classifications

  • Construction work

Tags

  • tender

Submission Deadline

8 months ago

Published

9 months ago

Description

GMCA are seeking to provide a new HWRC facility at Reliance Street to improve recycling
rates, improve traffic management and provide improved waste segregation. The existing
facility is an aging asset with a small and inefficient layout.
The proposed development has been designed to ensure efficiency of movement from both
public and operational perspectives, from a public point of view, this means provision of
separate entrance and exit off Reliance Street and provision of double lane width around
the one-way system.
This layout will improve access and traffic management particularly in higher volume
periods, allowing Suez to safely manage traffic during higher demand periods.
The scope of the works for related to the proposed HWRC includes, but is not limited to:
 Site establishment – accommodation, welfare and enabling works.
 Site clearance works
 Demolition and removal of structures, slabs and services
 Ground works, all below ground construction and drainage activities
 Pilling works and structures, concrete works and surface finishes as per the tender
drawings and pilling details provided in Appendix D – Kellers Pilling Proposal
 Boundary fencing, railings, access stairs and barriers
 All white lining and pedestrian line colour markings and site signage.
 Installation and integration of re-use shop and welfare building (Reuse container and
welfare building to be supplied by GMCA)
 Electrical, Lighting, CCTV and other service installations
 All required testing and commissioning
 Site De-mobilisation
 Project completion

Similar Contracts

Open

Ardersier Port, Phase 2 - Quay Civils (300m)

Quayside Civils (These works are the focus of this PQQ) - Setting up principal contractor welfare area including all temporary service connections, - Breaking out and disposal of concrete guide walls following installation by quay wall contractor, - Removal of piling mat, installed by Others, - Cropping of diaphragm wall to cut off level. - Reinforced concrete capping beams, to both quay and anchor wall, with a design life of 100 years to tie in with the Phase 1 quay, Including the supply and installation of all quay furniture cast in elements. - Removal of existing sheet pile quay wall, anchor wall and tie rods. - Excavation to tie rod level, approximately +0.0mCD, including dewatering system to facilitate, - Installation of tie rods (free-issue) between quay and anchor walls, - Backfilling above tie rods to formation level using site-won material, - 100m wide quay apron along the entire length of the new quay including capping layer and unbound stone pavement, - 250kPa uniform loading capacity, - Finished level of +6.5mCD (varies depending on drainage falls), - Installation of temporary and permanents sheet piles, - Infiltration drainage system with trenches as required, - Quay furniture including flexible mooring and berthing equipment such as pneumatic fenders, removeable bollards, and safety equipment inclusive of all associated cast in items, - Instrumentation and monitoring equipment associated with the quay wall. - Upgrades to the existing quayside which extends east beyond the new Phase 2 300m diaphragm wall and apron by approximately 758m, whilst retaining the existing quay wall, to extend the usable quayside (dredged by others). There will be a requirement for the Contractor to coordinate elements of works with the Clients quay wall and landside civils principal contractors. There is potential for the works to be varied to extend the new quay wall and quay wall civils further than the initial 300m.

AI Bid Assistant

Our AI-powered tool to help you create winning bids is coming soon!

View Contract Source Save Contract

Timeline complete