A38-A419 Whitminster Roundabout Canal Bridges

Award

Value

£2,500,000

Classifications

  • Construction work

Tags

  • award

Submission Deadline

5 years ago

Published

6 months ago

Description

The scheme shall ultimately deliver the construction of the canal through the A38 Whitminster Roundabout.  The scheme shall include the construction of two new bridges, a canal channel within the roundabout and a towpath under the bridge, the work consists of the following: -
•	The procurement, design and construction of two precast segmental box culverts (16m length, 7.45m clear span and 4.69m internal height).  To include headwall beam and N2 parapets.
•	Coordination of utility diversions including Severn Trent Water Main and W&W Gas Main.
•	Coordination of utility lifting and protection to include 13No BT Ducts, Vodafone, 2 No CityFibre, 2 No COLT and Virgin Media.  This will include procurement, design and erection of a service bridge to carry existing BT ducts when lifted to the required height.
•	Construction of 6 No contiguous bore piled wing walls
•	Construction of 2 No modular concrete block wing walls
•	Construction of a canal channel between the two bridges within the centre of the roundabout, to include provision of a towpath and embankment retaining wall.
•	Carriageway surfacing, kerbing and footpath amendments where the carriageway level will require raising to pass over the bridges.
•	Partial replacement of the street light system on the roundabout
•	Installation of N2 Vehicle Restraint Systems on the bridge approaches
•	Installation of pedestrian guard railing
•	Drainage amendments and partial culverting of the southern drainage ditch.  Installation of 2 No oil interceptors prior to discharge into the canal.
•	General vegetation and tree removal
•	Excavation and transportation of up to 14,000m3 of material to a site in Northleach where it will require placement over a designated field.
•	Replacement of road signs
•	Roadmarking reinstatement
•	Provision of 2 No ladders and horizontal recycled plastic fenders to be fixed to the towpath retaining wall
•	Media support during construction including time-lapse cameras, webcam and regular aerial images.

Tender period				:30th August 2019 to 4th October 2019
Anticipated Works Start Date 	:2nd December 2019
Completion				:16th October 2020
Indicative Value			:£2.5m

The proposed procurement route will be a single stage (sub-OJEU Open Procedure) using the NEC4 ECC form of Contract, Option A Priced Contract with Activity Schedule.

Full details will be available in the tender pack.

Documents

Premium

Bypass the hassle of outdated portals. Get all the information you need right here, right now.

  • Contract Agreement

    The official contract terms, conditions, and scopes of work.

    Download
  • Award Notice

    Details on the tender award and selected suppliers.

    Download

Similar Contracts

Open

B2G MWX: Minor Works and all associated works, supplies and services

B2G MWX will supersede and unify B2G's MW20 (national) and MW21 (regional) minor works frameworks, both of which are due to expire during Q1 2024, and will incorporate features successfully introduced in later frameworks, This framework will enable any UK contracting authority to procure one-off projects, programmes or term contracts to deliver both major or minor planned and/or responsive works in the construction, repair, maintenance and improvement of both housing and non-housing. This framework will be suited to principal contractors with multi-discipline capability, who operate both nationally and/or regionally, given that it will operate as a single UK lot, within which contractors have the option to designate 'active regions' and specialist 'work types'. Specialist contractors may also prefer to register for the B2G DPS, which operates in tandem with all B2G frameworks. However, whether framework or DPS, we set the bar high, and only appoint suppliers who are competent and competitive. Bid teams please note: The framework value is £200m PER ANNUM. nb. B2G frameworks operate on a 12 month auto-renewable basis (see note IV.1.3 within this notice) to maximise value of participation whilst minimising impact on bid team resource. And since the best suppliers usually have the busiest bid teams, our bid docs are designed to minimise bid team workload, with a focus on 'evidence not essays' and a simplified pricing format in sync with the UK gov's Should Cost Model.

AI Bid Assistant

Our AI-powered tool to help you create winning bids is coming soon!

View Contract Source Save Contract

Timeline complete

Publish
Bid
Evaluate
Award
Complete