Nutrient Neutrality -Full Feasibility Assessment of the Potential for the Development of Constructed Wetlands within Norfolk

Complete

Value

£48,000

Classifications

  • Environmental services

Tags

  • tender

Submission Deadline

11 months ago

Published

11 months ago

Description

Further feasibility work should provide the following information in report form. The work should be informed by the initial pre-feasibility report, 'Pre-Feasibility Assessment of the Potential for the Development of Constructed Wetlands' dated 03/05/2023. The report should provide the confidence to proceed to 'design and build' phases or the rationale for not proceeding with wetland implementation. 
Full feasibility Specification 
The key deliverable for this contract will be:
I.	Build on the 'pre-feasibility reduction figures' through identification of the possible range, ie minimum and maximum, for nutrient reduction capacity of the site, via wetland creation, for Nitrogen and Phosphorus using:
a.	Transfer abstraction of water from the relevant watercourse and;
with generated reductions calculated using: 
i.	One of the following methods with a supporting narrative
-	P-k-C* model
-	k-C* model
-	regression equation
ii.	Details of potential Flow
-	Flows of water from the relevant source
-	Inflow of other water sources
-	Variability of flow with time
iii.	Details of Concentration within Flow
-	Nitrogen and Phosphorus loads within all water sources considered 
-	Variability of the quality with time 
iv.	Refinement should enhance reduction calculations by ensuring the most relevant/localised data is used. Including:
-	A water balance calculation
-	Estimated sediment accumulation rates

2.	Clarification of design objectives in terms of the site's capacity to generate nutrient reductions for N and P in the context of:

-	Define the potential biodiversity impacts of:
o	potential loss of ditch/stream (where relevant)
o	water impoundment/abstraction 
o	water temperature impacts through wetland transfer

-	Carry out soil substrate investigations to determine:
o	potential for groundwater interaction
o	the extent of clay onsite
o	whether the wetland requires a clay or artificial liner  
o	if soil nutrient levels pose a risk of 'treatment liability' in terms of nutrient leaching

-	Development of a monitoring and baselining strategy, including:
o	identification of suitable monitoring points at in-flow and potential out-flows
o	flow and nutrient concentration monitoring 

-	Ranged cost estimates of:
o	implementation and construction 
o	performance monitoring to equilibrium 
o	annual wetland maintenance 

-	Carry out a desk-based assessment to identify any risks that may impact design or construction of the wetland from:
o	archaeological areas on-site
o	utilities on-site

-	Define the potential impacts of 'urban runoff' on wetland effectiveness (where relevant) including but not limited to: 
o	contaminate collection and discharge risk
o	contaminate effect on biological processes on wetland plants

DESCRIPTION CONTINUES IN ADDITIONAL TEXT SECTION

Additional information: 3.	Feasibility Assessment including constraints and options assessment covering:  
-	Topography
-	On-site Soil & Water sampling and analysis 
-	Geology & Hydrogeology
-	Groundwater protection, 
-	Hydrology & drainage
-	Flood risk
-	Protected sites & species
-	Land use, Historic landfill & Contaminated Land
-	Estimated costs of potential wetland design, construction, monitoring and maintenance

The above should be influenced by the provided 'site pre-feasibility' report and be undertaken within scope of the 'Wetland Mitigation Framework' 

Purpose of this Contract
To support the Nutrient Neutrality project's habitat delivery enabling Natural England, landowners and other interested parties to understand constraints and likely costs of progression towards the design and build phase of schemes.

-----

To apply for this opportunity you must submit your quotation meeting the requirements detailed in the Request for Quotation (RFQ) attached.
Your response must be sent to [email protected] by 17:00 on 20th October 2023

If you have any clarification questions linked to this opportunity or the procurement process please submit these via email to [email protected]. Please note that, unless commercially sensitive, both the question and the response will be circulated to all tenderers.

Documents

Premium

Bypass the hassle of outdated portals. Get all the information you need right here, right now.

  • Contract Agreement

    The official contract terms, conditions, and scopes of work.

    Download
  • Award Notice

    Details on the tender award and selected suppliers.

    Download

Similar Contracts

Open

Guidance for when undertaking noise impact assessments for pile driving in the marine environment

To develop and produce guidance for industry to undertake underwater noise risk assessments for pile-driving operations in the UK, focussed on the risk of injury to marine mammals and fish. To meet the offshore renewable energy targets set out by the UK government and devolved administrations, a substantial increase in the number and size of offshore wind farms will be required. This, in turn, may result in a considerable increase in the amount of impact piling being carried out within UK waters (including English, Welsh, Scottish, N.Irish, inshore and offshore). Piling can be used for the installation of both fixed and floating windfarms and well as other structures such as harbour pontoons, and involves forcing a supporting or retaining structure into the seabed using a hydraulic hammer. To meet the overall aim of this project (Section 2), the objectives are: 4.1. Review key publications relating to underwater noise risk assessments of piling noise (e.g. source characterisation, sound propagation, sound exposure modelling and criteria) summarising new findings as well as recommended methods for improving noise risk assessments of the risk of injury to marine mammals and fish from piling. 4.2. Based on the outputs of Objective 1, develop detailed guidance for assessing the risk of injury to marine mammals and fish posed by piling noise in UK waters. 4.3. Discussion of potential further improvements to noise risk assessments that may be possible to implement in piling assessments in the short to medium term. Available budget The total value of this project is £60,000 (GBP) including VAT If interested in this project potential bidders are invited to download the following documents and complete the conflict of interest form and the acceptance form of our terms and conditions attached to the invitation to tender letter (ITT). Additional information: The tender deadline for bid submissions has been extended from 16:00 hours on Monday 23 September 2024 to 16:00 hours on Monday 30 September 2024. **Bid submissions **Please use V2 tender Zip pack, the documents within the zip have been updated to reflect this change.

JNCC SUPPORT CO

Published 3 days ago

AI Bid Assistant

Our AI-powered tool to help you create winning bids is coming soon!

View Contract Source Save Contract

Organisation

Rupert Hammond

[email protected]

7435870160

Timeline complete