WP57 - Anti Graffiti

Award

Value

£25,000

Suppliers

Classifications

  • Railway bridge construction work

Tags

  • award

Submission Deadline

3 years ago

Published

3 years ago

Description

Apply Anti-Graffiti to below Bridge Structures in Railway environment:
      - NE & SE Wingwall (including precast elements)
      - East Abutment (including Stage 1, precast, and stage 2 pours)
      - West Abutment Caisson Cap
      - West Abutment Stem (including bearing plinths)
      - Ballast Wall (front face only. 2no.)
      - Bearing Plinths
      - Diaphragm Wall
      - Robust Kerb
      
      - All coatings to be applied in accordance with 146588-SKA-SPE-ECV-000012
      - Treatment is to be either Epicuro Hydrophobic Bridgeguard or Parex Paraguard
       
       Tenderers will be issued a formal invitation to tender (ITT) with a pricing and submission document to complete.
      
      The submission will included a balanced scorecard requesting answers to questions (along with evidence) to be submitted for review and scoring. The highest scoring tenderers will be considered preferred tenderer for the works. High level criterial of the balanced scorecard questions will include:
      - Quality
      - Sustainability
      - Competence
      - Commercial Price
      - Etc
      
      Mid tender reviews will be held prior to the submission deadline to review the scope of works with the SAS13 project team. Following the submission deadline, there will be post tender reviews to review your submissions with the SAS13 project team.
      
      Best and final offers may be requested from tenderers. 
       Skanska have been employed by Network Rail (NR) to replace the existing SAS 13 bridge to increase lateral clearance below the structure to enable the construction of HS2's new depot access lines and access to the new HS2 depot via road. The existing bridge forms the rail intersection between the Stechford to Aston (SAS) line and the Birmingham to Derby Line (DBP3).
      
      The new bridge will be a 92m single spanning structure. Skanska's appointment by Network Rail includes the design and demolition of the existing bridge and installation of the new structure.

Documents

Premium

Bypass the hassle of outdated portals. Get all the information you need right here, right now.

  • Contract Agreement

    The official contract terms, conditions, and scopes of work.

    Download
  • Award Notice

    Details on the tender award and selected suppliers.

    Download

Similar Contracts

AI Bid Assistant

Our AI-powered tool to help you create winning bids is coming soon!

View Contract Source Save Contract

Organisation

Tom Goodwin

[email protected]

3301050135

Timeline complete

Publish
Bid
Evaluate
Award
Complete